Project schedules have to be realistic, providing for a time lag between grant/loan approval and effectivity, incorporating doable timeframes for contract processing, and clearly indicating the target dates for the completion of all key activities.
Project Name
Rural Energy Project
Project Number
45303-001
Report Date
Report Source
Self-evaluation
Country