The economic value of existing water supplies, the critical factor in determining the project economic performance, was inadequately defined. At the very least, analysis should have been undertaken using realistic time savings resulting from reticulated water for women and children, with the basis for valuing time clearly outlined.
Report Date
Project Name
Central Region Rural Water Supply and Sanitation Sector Project
Project Number
40364-013
Report Source
Validation of self-evaluation
Country
Viet Nam
Sector
Themes
Applicability
Results framework and methodology level