The project's geographical coverage posed a major challenge to monitor subproject implementation in 12 project towns located all over the country from the northern tip (Phongsali) to the south (Samakkhixai). Particularly during rainy season, it was time-consuming for project coordination unit (PCU) staff and consultants to travel to the project towns, as well as for personnel from UDAAs and project implementation units (PIUs) to attend meetings and workshops. Due to its underestimation at appraisal, insufficient travel budget hindered effective monitoring of subproject implementation in the project towns.