Delays in implementation ensue when components are clustered in a project. Further, clustering discourages ownership of project outputs. Combining harbor development with coastal conservation delayed project implementation considerably because the activities are not complementary.
Project Name
Coastal Resource Management Project
Project Number
31287-013
Report Date
Report Source
Self-evaluation
Country
Themes