The project schedule was unrealistic for a complex project that relied heavily on existing capacity and several up-front conditions before the subproject investments. The scheduling of complex sector and policy loan projects has to be improved and streamlined on the basis of actual implementation experience.
Report Date
Project Name
North-West Frontier Province Urban Development Sector Project
Project Number
27182-013
Report Source
Self-evaluation
Country
Pakistan
Sector
