North-West Frontier Province Urban Development Sector Project

The project schedule was unrealistic for a complex project that relied heavily on existing capacity and several up-front conditions before the subproject investments. The scheduling of complex sector and policy loan projects has to be improved and streamlined on the basis of actual implementation experience.

Project Name

North-West Frontier Province Urban Development Sector Project

Project Number
27182-013
Report Date
Report Source
Self-evaluation
Country
Report Rating