Clarifying each cofinancier's policy and administration with respect to all the subprojects/project components within its scope is critical to minimizing the implementation risks that may be encountered in parallel cofinancing.
Project Name
Power System Expansion and Efficiency Improvement Investment Program – Tranche 1
Project Number
42378-015
Report Date
Report Source
Self-evaluation
Country