Harbin Water Supply Project [Loan 1995-PRC]

The commitment shown by ADB and the HMG was fundamental to the project’s success. Careful assessment and project design during loan processing, detailed procurement and implementation planning, and timely availability of counterpart funding and decision making ensured smooth implementation and commissioning of the project about 1 year ahead of schedule.

Report Date
Project Name

Harbin Water Supply Project [Loan 1995-PRC]

Project Number
33177-013
Report Source
Independent project evaluation
Country
China, People's Republic of
Report Rating
Successful