Enhancing the Institutional Capacity of the Implementation Monitoring and Evaluation Division

During TA design stage, government’s confirmation should be obtained to ensure that counterpart staff for ADB TA consultants are identified and available for appropriate and/or adequate guidance and coordination of work. For this TA project, Project Director was changed three times, officials were assigned part_x005F_x0002_time basis on additional charge.

Project Name

Enhancing the Institutional Capacity of the Implementation Monitoring and Evaluation Division

Project Number
48139-001
Report Date
Report Source
Technical assistance completion reports
Country