Improving Energy Efficiency, Emission Control, and Compliance Management of the Manufacturing Industr

Consultants’ terms of reference should be based on milestone deliverables (final reports, surveys, workshops/training events, and others) submitted officially to ADB and executing agency/implementing agency, and not time-based contracts. To ensure the quality of milestone deliverables, it is useful to have an effective mechanism established as part of the TA design to ensure a critical review process of the deliverables and require the consultants to rework unsatisfactory deliverables at no or limited additional costs.

Project Name

Improving Energy Efficiency, Emission Control, and Compliance Management of the Manufacturing Industr

Project Number
48005-001
Report Date
Report Source
Technical assistance completion reports validation