Due consideration to realistic timeline and risk mitigation. The project was designed to be completed in 4 years but after 10 years, it is still incomplete. The timeline of 4 years at appraisal seems over-optimistic. In particular, the following factors should also be considered in this type of projects: (i) bridging language barriers, (ii) knowledge of local accounting regulations, and (iii) adequacy of locally based technical staff. Assessment of these factors and incorporation of corresponding risk-mitigation measures could help minimize delays in project implementation.