While land permits are expected to be obtained before loan signing, it is important to include a strategy in the stakeholders analysis to ensure continued support from stakeholders even after the land permits have been obtained by the project. This is to minimize unforeseen rejection by stakeholders.
Project Name
Java-Bali 500-Kilovolt Power Transmission Crossing Project
Project Number
42362-013
Report Date
Report Source
Self-evaluation
Country