As the TCR stated, other factors (often political) play an important role and are beyond the control of a TA project. Therefore, a broader lesson learned could be: Clearly aligning the intended outcome with its indicators and TA project’s outputs is critical for avoiding any attribution issues. In this TA project, the intended outcome was dependent on many other external factors over which the TA project had no control.
Project Name
Reforms in the Public Sector Compensation System
Project Number
48459-001
Report Date
Report Source
Technical assistance completion reports validation
Country
Topics