While the project-preparation facilities made sense, the TA loan itself was spread too thinly. The funds were dispersed across three sectors, and were handled by numerous agencies managing subprojects in many locations. This made coordination a challenge right from the outset, especially given the absence of an experienced and capable local coordination team. It did not work. In retrospect, the multi-sector design of the TA was wrong, and approval should not be given for similar TA loans in the future. The important lesson learned here is to restrict loans to one sector at a time.

Report Date
Project Name

Infrastructure Development

Project Number
38458-013
Report Source
Self-evaluation
Country
Pakistan
Report Rating
Less than successful