The Planning and Development Division's (PDD lack of capacity to assist the implementing agencies delayed the issuance of consultant mandates, thus slowing down work on some priority subprojects. The choice of the PDD as the executing agency was a mistake. The PDD lacked qualified staff,, access, and a track record. The setting up of new units to manage consultancy contracts does not work and should not have been proposed in the first place.

Report Date
Project Name

Infrastructure Development

Project Number
38458-013
Report Source
Self-evaluation
Country
Pakistan
Report Rating
Less than successful