Jammu and Kashmir Urban Sector Development Investment Program (Project 1)

Subproject’s scope should be oriented toward outcomes and provide comprehensive end-to-end solutions for the entire target area, such as 24×7 water supply with 5–10 years of O&M, subject to capacity of the asset operator.

Project Name

Jammu and Kashmir Urban Sector Development Investment Program (Project 1)

Project Number
41116-023
Report Date
Report Source
Self-evaluation
Country
Report Rating
Applicability