Financial management staff’s inclusion in review missions will be key to ensuring improved financial performance of future projects. Neither the ADB project team nor PCO could decipher financial management requirements and covenant quantifications due to the absence of financial management staff in review missions. The team failed to follow up on audit opinions and recurrent issues, leading to recurrence of the same issues and delays in submitting the APFS. This improved only after inclusion of a financial management staff toward the end of the project.