During the implementation of Part C, the change in construction method from labor to equipment based (otta seal standard) had an effect on the original road length. Detailed study on the construction method needs to be carefully undertaken during the design phase to avoid changes during the implementation phase.
Report Date
Project Name
Road Network Development Project
Project Number
29472-013
Report Source
Self-evaluation
Country
Nepal