The project was implemented during the conflict period (2001-2006) and it faced challenges from local communities, which made additional demands and at times disrupted the work progress. Part A could not be completed as it was highly affected by unrest in Terai. A proper analysis of road design and selection of road sections should be carried out during the design phase to ensure timely completion of the selected road sections is possible.
Project Name
Road Network Development Project
Project Number
29472-013
Report Date
Report Source
Self-evaluation
Country