Premature fielding of an MTR mission can restrict its ability to capture the need for adjustments in the project scope, targets, and timeline, consequently affecting project performance rating.
Report Date
Project Name
Second Crop Diversification Project
Project Number
40534-013
Report Source
Self-evaluation
Country
Bangladesh
Sector
Applicability
Project Cycle Stage
Implementation
Topics