Skip to main content
Evaluation Lessons
  • Home
  • Countries
    • Afghanistan
    • Armenia
    • Azerbaijan
    • Bangladesh
    • Bhutan
    • Brunei Darussalam
    • Cambodia
    • China, People's Republic of
    • Cook Islands
    • Federated States of Micronesia
    • Fiji
    • Georgia
    • Hong Kong, China
    • India
    • Indonesia
    • Kazakhstan
    • Kiribati
    • Kyrgyz Republic
    • Lao People’s Democratic Republic
    • Malaysia
    • Maldives
    • Marshall Islands
    • Mongolia
    • Myanmar
    • Nauru
    • Nepal
    • Niue
    • Pakistan
    • Palau
    • Papua New Guinea
    • Philippines
    • Republic of Korea
    • Samoa
    • Singapore
    • Solomon Islands
    • Sri Lanka
    • Taipei,China
    • Tajikistan
    • Thailand
    • Timor-Leste
    • Tonga
    • Turkmenistan
    • Tuvalu
    • Uzbekistan
    • Vanuatu
    • Viet Nam
    • Australia
    • Japan
    • New Zealand
  • Sectors
    • Agriculture, natural resources, and rural development
    • Education
    • Energy
    • Finance
    • Health
    • Industry and trade
    • Information and communication technology
    • Multisector
    • Public sector management
    • Transport
    • Water and other urban infrastructure and services
  • Themes
    • Inclusive Economic Growth
    • Environmentally Sustainable Growth
    • Regional Integration
    • Private Sector Development
    • Governance and Capacity Development
    • Gender Equity and Mainstreaming
    • Knowledge Solutions
    • Partnerships
  • About
  • Home
  • Countries
  • Sectors
  • Themes
  • About

Cyclone Pam Road Reconstruction Project

An ongoing commentary on critical path cumulative delays needs to supplement the time management mechanisms of the FIDIC works contract.

Project Name

Cyclone Pam Road Reconstruction Project

Project Number
49319-001
Report Date
31 Dec 2021
Report Source
Self-evaluation
Country
Vanuatu
Sector
Transport
Road transport (non-urban)
Transport policies and institutional development
Applicability
Project-level
Project Cycle Stage
Implementation
Topics
FIDIC contracts

Related Lessons

For investments of a regional character, it is important to assign economic benefits to the appropriate country, if not, economic viability of the…


Changes in government could trigger changes in counterpart agencies and priorities with significant implications on program design and…


It is important to perform an adequate due diligence at appraisal to develop a realistic project schedule that duly considers the borrower's…


Project benefit identification, quantification, and valuation depend on the establishment and effective use of
PPMS. The project was not…


Before implementing any additional works or contract variation, there should already be agreement on the works to be done and the commensurate…


Subscribe to our mailing list

6 ADB Avenue,
Mandaluyong City
1550, Metro Manila,
Philippines

 

Phone: +632 632 4444
Fax: +632 636 2444

Other ADB Websites

ADB Compliance Review Panel
Asia Pathways (ADBI Blog)
Asia Regional Integration Center
Asian Bonds Online
Asian Development Blog
Open Access Repository
Statistical Database System

IED Social Media

LinkedIn

Facebook

Twitter

YouTube

©2021 Independent Evaluation - Asian Development Bank

Footer

  • About