Project readiness. Advance procurement was used for the first time in the recruitment of consultants under a project with Directorate General of Highways (DGH), and consultant recruitment was not a cause of delays. The time for completing the procurement process for the civil works, however, was underestimated; the process took 1 year longer than planned. The lesson here is that the time required for completing the various steps has to be estimated much more carefully, on the basis of experience.
Project Name
Road Rehabilitation - 2 Project
Project Number
34159-013
Report Date
Report Source
Self-evaluation
Country