It is important to properly sequence the implementation of technical assistance so it could provide its inputs to the project in a timely manner. According to the project completion report, the delay in the development of the National Transport Plan supported by the project preparatory TA affected project implementation as projects sites were required to be included in the plan prior to implementation.
Report Date
Project Name
Domestic Maritime Support (Sector) Project
Project Number
40263-022
Report Source
Validation of self-evaluation
Country
Solomon Islands
