The level of institutional
capacity and limitations of the executing agency are crucial factors that need to be carefully developed on time. Furthermore, the experience of the borrower and executing agencies in
managing ADB-financed projects needs to be duly taken into account during risk assessment to
provide the necessary capacity building and skills set prior to execution of a project.
examined during project appraisal to effectively support project implementation. Identification of
the capacity risks related to procurement and management, and operational risks at the onset
could be appropriately addressed during design phase and mitigation measures could be