The flexibility of EAL allows the design and monitoring framework (DMF) to be enhanced during
implementation. This was not fully maximized in this project. Other than adding project outputs
under the additional financing, outcome indicators remained to have attribution issues. Outcome
indicators for improved transport infrastructures could have helped provide data to calculate EIRR
at completion (para. 13). Quality review, including interdepartmental review at appraisal, can
provide guidance in this regard.
Project Name
Cyclone Pam Road Reconstruction Project
Project Number
49319-001
Report Date
Report Source
Validation of self-evaluation
Country