Road Corridor Investment Program (Tranche 1)

Extensive delays in implementing a project that is not ready for implementation reflect foregone economic benefits and result in a net loss to the economy. Assessment of project readiness is an integral part of the project preparation process, particularly from a safeguards perspective where delays often originate.