Diligent project financial monitoring enables savings to be identified at an early stage, making it possible for additional components to be undertaken thereby improving project results and benefits. The project's executing and implementing agencies identified some savings after the award of two original works packages. This enabled an additional works package to be prepared, procured, and executed within the extended implementation period.
Project Name
Thimphu Road Improvement Project
Project Number
44240-014
Report Date
Report Source
Self-evaluation
Country
Themes