North Karnataka Urban Sector Investment Program - Tranche 3

Systematic analysis of market capacities and pragmatic cost estimation for better packaging options could avoid procurement delays and rebidding because of poor bidder participation. Considering the remoteness of the project locations and the market capacities, the EA modified contract conditions for sewerage network contracts to attract bidders. Despite modifications, poor response from bidders continued, resulting in repeated rebidding. These challenges prompted the EA to institutionalize measures to strengthen capacities to procure and execute complex contracts, including performance-based maintenance contracts, by conducting training programs for contractors in the state, particularly in the hinterland.