A longer project implementation period is necessary in projects with geographically challenging state terrain. The completion of this project was extended twice, for a total of 18 months, basically because of startup delays. Despite the delays that amounted to 30% overrun, completing the project in 6.5 years is a remarkable achievement for a first-time executing agency and for the first multisector project in the human development sector in a geographically challenging terrain.