National Highway Network Development in Balochistan Project

Lack of continuity in the staff of key project agencies could lead to chronic implementation delays. Procurement of works and recruitment of consultants followed due process and were completed; albeit with delays. Although NHA has carried out procurement for multiple MDB-financed projects; a lack of continuity of key staff at its Procurement and Contract Administration posed challenges for each procurement and this project was no exception. Procurement consultant support is a regular feature provided by ADB. Although LARP implementation was completed before execution of works; however; a legal matter led to project implementation delays.