Himachal Pradesh Clean Energy Development Investment Program (Tranches 1 and 2)

Significant implementation delays under both tranches underscore three important points: (i) weather conditions stop works during winter months and even interrupt work during other months, (ii) proper planning is essential so that issues such as inadequate access infrastructure can be taken care of sufficiently in advance, and (iii) extensive geological surveys and testing are crucial in the Himalayan region prior to the detailed project report stage. The latter can also contribute to making realistic cost estimates, preparing robust bidding packages with appropriate contractor selection criteria, and better contractor selection. Additionally, the need for quality assurance and quality control cannot be doubted.