Closer communication and coordination between ADB and the implementing agencies (IAs) are necessary to ensure timely loan closing. The loan closing took about 21 months. One of the major reasons was that some of the withdrawal application papers submitted by the IAs were incomplete or inconsistent and clarifications or corrections of these took a long time. ADB’s review and clearance on these clarifications was also slow in several cases.