Incorporating utility shifting as part of the item-rate contract has proven effective for timely project completion in some Indian states. Utility shifting is usually contracted
out to a third-party entity specialized in utility shifting. Contractors often abuse this arrangement, however, taking it as an excuse to delay civil works. To prevent this, the utility shifting should be included as an item in the bill of quantity to be carried out directly by the contractor.