Each year, the project encountered a delay in budget allocation or Daftar Isian Penggunaan Anggaran (DIPA) release, which resulted in delays in implementing planned activities. This could have been avoided if the government had allowed multi-year budget earmarking, given that the project was funded by a multi-year loan. Since this has been identified as a broad systemic issue affecting other projects, this is also being addressed in the Country Portfolio Review Mission jointly held by ADB and Badan Perencanaan dan Pembangunan Nasional (National Development Planning Agency) or BAPPENAS.