Estimation of the project cost requires a greater anticipation of potential cost overrun/underrun that may arise during implementation. During appraisal, a more in-depth examination and consideration of factors related to currency depreciation permits a more robust and realistic cost estimates. Under this project, a substantial loan amount was cancelled due to the rupee depreciation. A careful financial planning and cost projections coupled with risk mitigation measures and monitoring allows for better utilization of loan proceeds.
Project Name
Jaipur Metro Rail Line 1-Phase B Project
Project Number
46417-001