Second Rural Connectivity Investment Program - Tranche 1

Land acquisition should be embedded in transport policies. As of 2022, the Prime Minister's Rural Roads Program (PMGSY) was being implemented with no land acquisition. Where land is required, only voluntary-based possession is allowed. If sufficient land cannot be pooled on a voluntary basis, geometric design is being compromised. These locations may become accident black spots. Thus, policy amendment is needed in cases where sufficient land for improvement is unavailable voluntarily; permission should be granted for acquisition of land.