In addition to ensuring robust environmental assessment and management to avoid project delays and operational disruptions, it is imperative to plan for and link mitigation measures such as the installation of bird flight diverters to the commissioning of power lines and financial closure, rather than leaving such measures to be retrofitted after the power lines have become operational. Insufficient attention to forest clearance needs during project design and planning resulted in implementation delays. The quality of the environmental assessments fell short.