Strong collaboration between the executing agency and the land office from the project planning stage is critical to minimize delays in land acquisition completion and land ownership update.
Report Date
Project Name
West Kalimantan Power Grid Strengthening Project
Project Number
41074-013
Report Source
Self-evaluation
Country
Indonesia
Applicability
Project Cycle Stage
Implementation