Use of existing project management units (PMUs) in the executing agency enables timely start and implementation. The project largely benefited from the use of the executing agency's existing PMU, which was actively involved in grant processing and in facilitating grant approval and ratification by the central and provincial governments. The PMU professionally handled the advance contracting action for the selection of a detailed engineering and design consultant, which was mobilized within 1.5 months of grant effectiveness. This proactive action enabled a prompt project startup and timely implementation and led to the project's closing by the original target date.
Project Name
Managing Solid Waste in Secondary Cities
Project Number
52303-001
Report Date
Report Source
Self-evaluation
Country
Applicability
Project Cycle Stage
Implementation