Stronger due diligence on the part of ADB would have identified risk earlier and reduced project delays. The inability of PNCC to raise funds for the project, too, should have been anticipated at a time when most government corporations were strapped for cash and that PNCC had few alternative revenue sources apart from government subsidies. It should have been foreseen that PNCC would need to reduce its exposure in the project.
Project Name
North Luzon Expressway Rehabilitation and Expansion (Loan 7162/1769)
Project Number
33924-014
Report Date
Report Source
Independent project evaluation
Country