Addressing the fundamentals reforms upfront: Major governance issues of autonomy and incentives to perform, which plagued the key implementing agencies that were the urban service providers, were only captured piecemeal in the policy framework. This allowed these issues that were fundamental for the success of the project to be addressed (or not be addressed) during project implementation. The design also allowed major investment subprojects to be implemented without addressing these fundamental issues. All critical conditions that are fundamental to project success should be part of project readiness at entry.
Project Name
Rawalpindi Environmental Improvement
Project Number
37003-013
Report Date
Report Source
Self-evaluation
Country
Sector