Schedule for implementation and financing. The WMG should have increased the wastewater tariff to raise the required funding instead of requiring the WUDDC to borrow more from domestic banks. The WUDDC�s audited financial reports indicate that its short-term indebtedness is much higher than the typical for such an enterprise. The more timely reallocation of unused loan proceeds could have achieved full utilization of the loan proceeds including savings on interest during construction. The finance department of the WUDDC should have monitored and controlled the implementation schedule and financing plan to minimize commitment charges.
Project Name
Wuhan Wastewater Management
Project Number
34472-013
Report Date
Report Source
Self-evaluation
Country