Basic Skills Development Project

To ensure proper sequencing and smooth coordination between components, the project implementation unit should have been responsible for the overall management of project components. The project provides for both software and hardware assistance as a comprehensive package. GTZ was financing the software side of the project and ADB provides for the hardware support. Since different departments in the Ministry of Labor and Human Resources managed the GTZ and ADB financed components, the sequencing of activities suffered. For example, equipment was selected ahead of the revision of curricula, and some equipment were inappropriate for the courses being offered. [Main text, paras. 33,42]

Project Name

Basic Skills Development Project

Project Number
31317-012
Report Date
Report Source
Self-evaluation
Country
Report Rating