Passing the Cooperative Societies Act, the necessary enabling legislation before subproject loan agreements were possible, was known at project approval to be the responsibility of Parliament and therefore something the government could guarantee. Yet project formulation as set out in the report and recommendation of the President (RRP) implicitly assumed that this legislation would be passed in a timely manner and offered no robust contingency plan should the legal entities to operate subprojects fail to materialize.