Rajasthan Urban Infrastructure Development Project

Achieving critical mass in the staffing of the PMU and project implementation units (PIUs) and retaining key staff members for the duration of the project are important factors in smooth implementation. A number of engineers involved in the project's design and familiar with packaging and contract conditions remained with PMU through implementation and greatly facilitated its execution.