At appraisal, the difficulty of implementing the Reform Program could have been foreseen and special measures for monitoring and supervision should have been proposed in the RRP, and specific milestone requirements to check the progress of the Reform Program should have been set.
Project Name
Road Sector Development Project (1986-SRI[SF])
Project Number
31280-013
Report Date
Report Source
Independent project evaluation
Country