Viet Nam’s procurement law prohibits executing and implementing agencies from issuing bidding documents until capital resources for the packages have been allocated. The procurement for complex projects may take more than 1 year from bidding documents’ issuance to contract awards. Applying ADB’s advanced actions can mitigate this procurement risk.
Project Name
Ho Chi Minh City Urban Mass Rapid Transit Line 2 Investment Program (Tranches 1 and 2, and Multitranche Financing Facility)
Project Number
39500-013
39500-023
Report Date
Report Source
Validation of self-evaluation
Country
Themes
Applicability