Shifting of utilities need to be included in civil works contracts to avoid delays in construction works and ensure that all utilities requiring shifting are shifted. This could also help prevent contractors from taking advantage of issues associated with utility shifting to their own benefit.

Report Date
Project Name

Second Rural Connectivity Investment Program (Tranche 2 and Multitranche Financing Facility)

Project Number
48266-002
48226-004
Report Source
Self-evaluation
Country
India
Report Rating
Applicability
Project Cycle Stage
Implementation