Skip to main content

Cyclone Gita Recovery Project

The establishment of a project performance management system (PPMS), which was not covenanted in the grant agreement, could have provided a useful source of data on which to develop an economic analysis model; identify, quantify, and value economic benefits; and assess the efficiency of the project. Because of the emergency nature of the project, baseline data could be collected during project implementation to enable data comparison after project completion.

Report Date
Project Name

Cyclone Gita Recovery Project

Project Number
52129-001
Report Source
Validation of self-evaluation
Country
Tonga
Report Rating
Project Cycle Stage
Preparation
Implementation