The establishment of a project performance management system (PPMS), which was not covenanted in the grant agreement, could have provided a useful source of data on which to develop an economic analysis model; identify, quantify, and value economic benefits; and assess the efficiency of the project. Because of the emergency nature of the project, baseline data could be collected during project implementation to enable data comparison after project completion.