Second Jharkhand State Road Project

Preparing, reviewing, and monitoring project cost estimates contribute to a more efficient utilization of project funds. A more in-depth assessment and consideration of currency depreciation factors during project appraisal permits a more robust cost estimate. Under this project, a substantial loan amount was canceled because of the rupee depreciation against the US dollar. In-depth financial planning and cost projections coupled with risk mitigation measures allows for better utilization of loan proceeds.

Report Date
Project Name

Second Jharkhand State Road Project

Project Number
49125-001
Report Source
Validation of self-evaluation
Country
India
Report Rating
Applicability
Project Cycle Stage
Preparation