A close coordination and efficient communication mechanism among agencies and project units that are part of the implementing structure is crucial for the timely identification of issues and resolutions. Adjustments in the detailed designs usually happen since issues or new findings arise at the actual sites. To resolve them on time, these issues need to be discussed by all agencies and units involved in the project. For instance, the introduction of the separation wall under this project was a new concept and could have been relayed to all relevant agencies and units in a timely manner. Another lesson is the need to have separate project teams that are responsible for the delivery of physical and nonphysical components of the project. These teams can provide sufficient technical and financial resources to implement and monitor the progress of each component.
Kulhudhuffushi Harbor Expansion Project